Week 2 – 26 June to 1 July

Well, this was certainly a week of messy progress, but certainly progress nonetheless!

I first drove past our block on Sunday afternoon, even though I’d been past on Friday evening, and lo and behold, some work had taken place over the weekend. The site had large holes bored throughout, I assume for the concrete piers to be placed under our slab, and looked a little like it had been bombed!

After receiving an email from Porter Davis on Monday indicating that our slab would be laid on 4 July, I couldn’t help but go past every second day to see whether we were actually going to achieve that goal.

Going past again on Wednesday revealed that order had been restored to the land and I could make out the concrete piers that had been placed where the bore holes had been previously.

By Thursday, brilliant white plastic tubes sitting proudly in crushed rock indicated that underground plumbing connections had been installed! Perhaps we will have a slab on Monday as promised!

This slideshow requires JavaScript.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s